Capital Improvement Projects in Progress Precinct 3

PUBLIC WORKS DEPARTMENT
Project:
Babcock Phase V
Precinct: 3
Location / Limits:
From
Camp
Bullis
to
Heuermann (Kyle Seale Pkwy
to Camp Bullis Rd).
Scope:
Reconstruction of Babcock Rd to
include two travel lanes and fourfoot
shoulders.
Roadway
reconstruction
will
provide
unflooded access to this segment
of roadway and will include the
construction of four bridges and a
bridge class culvert.
Status: Construction (52 %)
Additional Information:
Consultant: TEDSI
Bid Opening: July 1, 2013
Contractor: J3 Companies LLC
Construction Start: Nov. 19, 2013
Construction Cost: $ 8,566,353.95
Construction End Date: 1 Q 2016
Joint Bid: CPS & SAWS
With Flood Control Component
May 11, 2015
PUBLIC WORKS DEPARTMENT
Project:
Borgfeld Dr Phase I
Precinct: 3
Location / Limits:
From Timberline Dr to Hwy 281.
Scope:
Reconstruction
approximately
14,300 linear feet of Borgfeld
Road to a Secondary Arterial
Type “A” street and reconstruct
drainage culverts.
Streets
section will consist of a 56 foot
wide pavement, including four 12
foot lanes and 4 foot wide
shoulders, with roadside ditches.
Status: Construction ( 59 %)
Additional Information:
Consultant: Jacobs
Bid Opening : April 5, 2013
Contractor: SMC Contractors
Construction Start: July 15, 2013
Construction Cost: $ 8,696,305
Construction End Date: 3 Q 2015
Joint Bid: SAWS, CPS Gas
Bond 2003
May 11, 2015
PUBLIC WORKS DEPARTMENT
Project:
Borgfeld Dr Phase II
Precinct: 3
Location / Limits:
From Timberline Dr to FM 2696
(Blanco Rd) including Old
Blanco Rd south of Borgfeld
Drive.
Scope:
The project consists of 2 miles of
roadway reconstruction to two-12
ft. travel lanes in each direction
designated
turn
lanes
at
intersections,
two
4-foot
shoulders
and
necessary
drainage.
Status: Final Design
Additional Information:
Consultant: CDS Muery Services
Advertise Date:
Contractor: TBD
Construction Start Date: 3 Q 2015
Construction Cost: $ 6,909,167
Construction End Date: 2 Q 2017
Joint Bid: TBD
May 11, 2015
4 Q 2015
PUBLIC WORKS DEPARTMENT
Project:
Boerne Stage Road
Precinct: 3
Location / Limits:
From Cross Mountain Trail to
Intersection of IH 10.
.
Scope:
The project consists of 1.1 miles
of roadway reconstruction to 2-12
ft. lanes and a 14 ft. continuous
center turn lane with a 6 ft.
shoulder in most sections. It also
consists
of
channel
improvements to Leon Creek and
drainage structure.
Status: Construction (76 %).
Additional Information:
Consultants: AECOM
Bid Opening: August 9, 2013
Contractor: Texas Sterling
Construction Start : Dec 2, 2013
Construction Cost: $ 8,171,894
Construction End Date: 3 Q 2015
Joint Bid: SAWS, CPS-Gas
With Flood Control Component
May 11, 2015
PUBLIC WORKS DEPARTMENT
Project:
Bulverde Rd Phase IV
Precinct: 3
Location / Limits:
Expansion of Bulverde Rd from
Marshall Road to approximately
6,300 ft. north.
Scope:
Project will expand the existing
two lane rural roadway section to
an urban roadway section
consisting of two 12 foot travel
lanes in each direction with a 14
foot center median/turn lane
within an 86’ ROW (Typical).
Status: Final Design
Additional Information:
Consultant: LAN Inc.
Advertise Date: 4 Q 2015
Contractor: TBD
Construction Start Date: 3 Q 2016
Construction Cost: $ 7,631,300
Construction End Date: 4 Q 2017
Joint Bid: SAWS , CPS Gas
MPO Project
May 11, 2015
PUBLIC WORKS DEPARTMENT
Project:
Bulverde Road Phase V
Precinct: 3
Location / Limits:
From the end of Bulverde Road
Phase IV (approx. 6,300 ft.
north of Marshall Rd) to
Smithson Valley Rd.
Scope:
Project will expand the existing
two-lane rural roadway section
to an urban roadway section
consisting of two 12-foot travel
lanes in each direction and 2 ft.
to 4 ft. shoulders within an 86’
ROW (typical).
Status: Construction (68 %).
Additional Information:
Consultants: HALFF
Bid Opening: Aug. 16, 2013
Contractor: Capital Excavation
Construction Start: Nov. 19, 2013
Construction Cost: $ 8,066,351
Construction End Date: 3 Q 2015
Joint Bid: SAWS, CPS-Gas
With Flood Control Component
May 11, 2015
PUBLIC WORKS DEPARTMENT
Project:
Bulverde Rd Pedestrian Amenities
Precinct: 3
Location / Limits:
Bulverde Rd from Evans Rd to
Marshall Rd.
Scope:
The proposed project will involve the
installment of pedestrian amenities
within the existing 86 foot Bulverde
Road right-of-way for the benefit of
area bicyclists and pedestrians
stretching 6,864 linear feet.
Status: Preliminary Design.
Additional Information:
Consultant: KLOTZ Associates
Advertise Date: TBD
Contractor: TBD
Construction Start Date: TBD
Construction Cost: 1,200,000
Construction End Date: TBD
Joint Bid: N/A
May 11, 2015
PUBLIC WORKS DEPARTMENT
Project:
Marshall Rd
Precinct: 3
Location / Limits:
From US 281 to Bulverde Rd.
Scope:
Roadway reconstruction and
expansion from a 2 lanes to a 3
lane urban configuration with
drainage
improvements
and
pedestrian amenities within a 80’
ROW (typical) . 4,800 L.F.
Status: R.F.Q.
Additional Information:
Consultant: TBD
Advertise Date:
Contractor: TBD
Construction Start Date:
Construction Cost: $ 3,000,000
Construction End Date: TBD
Joint Bid: TBD
May 11, 2015
TBD
TBD