20150407-TN-753-Roe Hwy closure UPDATED

7 April 2015
UPDATED: WEEKEND CLOSURE
13 March 2015
Roe Highway between Tonkin Hwy and Great Eastern Hwy Bypass
7pm, Friday 17 until 5am, Monday 20 April 2015
The Roe Highway / Berkshire Road intersection is being upgraded to a grade separated interchange,
interchange where Roe
Highway traffic will travel over the top of Berkshire Road, allowing a free-flow
free flow movement. To continue to progress the
upgrade of this intersection, the existing intersection and sections of Roe Highway must be temporarily realigned to
the north (towards the industrial area), opening up more work area to allow the bridge construction to start.
In order to allow the safe completion of the construction
and realignment of traffic onto the new temporary Roe
Highway / Berkshire Road intersection, the full closure
of Roe Highway is required. This closure has been
rescheduled due to wet weather.
Roe Highway between Tonkin Highway and Great
Eastern Highway Bypass will be closed to all traffic
from 7pm, Friday 17 April until 5am, Monday 20
April 2015.
During this closure, access to / from Roe Highway to /
from the adjoining roads along this section will also be
closed.
Enclosed are maps showing the location of this closure
and detour routes.
Signage will be in place to guide road users through
detour routes to complete their journey during this
closure.
Road users are strongly encouraged to plan their
journey to avoid the area if possible or allow extra travel
time.
The work is subject to weather and site conditions,
which may result in changes to this schedule. In the
event of changes, updated information will be available
on the project website.
Location of closure
Reference: GWA-WZ-COR-0510